Help

Help›Commitments›Change planned deliveries

Change planned deliveries

Reviewed Oct 29, 2026

View as Markdown
Words
TierPro
SeatA seat that can write and holds the Buy editor door, on a plan that includes Commitments
Ask TightlyMay propose it; you press

What it changes ​

Change planned deliveries records how a product's worked buy is meant to arrive. It takes one of two forms:

  • Delivery months: shares of the buy by month. The shares are percentages and must total 100%.
  • Dated deliveries: exact deliveries, each with a Planned receipt date, a Supplier, a Receiving warehouse and Inventory units for each variant.

It changes planned receipts only. It places no purchase order, changes no supplier order, and records no promise that goods have shipped. Clear schedule removes the recorded delivery plan; it does not set the buy to zero.

Who may press it ​

A seat that can write and holds the Buy editor door, on a plan that includes Commitments. Ask Tightly may propose saving or clearing a product's delivery plan. It reads the current schedule, states what it will do, and waits for your Yes or No. The confirmation is tied to the revision it read, so if someone changes the schedule meanwhile, ask again. Over MCP nothing here writes.

How ​

  1. In Buy plan, open the product. Its delivery section is headed Planned deliveries before the season and Delivery plan in season.
  2. For monthly shares, type a percentage for each month under Delivery schedule. The row reads Total with your sum, and Unsaved until you save. Press Save schedule. Reset discards your edit and Clear schedule clears the recorded plan.
  3. For exact deliveries, press Plan dated deliveries. Under Delivery 1 and onward, set the Planned receipt date, Supplier, Receiving warehouse, and units for each variant, and press Add delivery for another. The header reads "{planned} planned / {recorded} recorded units".
  4. Press Save deliveries.
  5. If the page says "Inputs changed since this draft.", press Keep draft with reviewed inputs after reading the refreshed options, or Review current inputs to refresh them yourself.

What you see ​

For months, the months offered are the ones the commitment's window covers. For dated deliveries, the drawer lists problems before it lets you save, for example "Delivery units must match the recorded buy.", "Record a buy quantity first." and "Complete the delivery dates, source and whole-unit quantities." Where supplier minimums are not met it says "Delivery quantities do not meet supplier purchase minimums." These are planning aids: a saved schedule is not a supplier commitment, and Sign off reviews the buy separately.

Through Ask Tightly the confirmation is one sentence, for example:

Save delivery months for product {product}: 2026-10: 25%, 2026-11: 75%. This changes planned receipts only.

Clear the recorded delivery months for product {product}. Supplier orders stay unchanged.

Save {n} exact planned deliveries for product {product}: {units} inventory units arriving {dates}. Supplier, warehouse, account allocations and planned payment dates are included as reviewed. Existing supplier orders stay unchanged.

What to do ​

To correct a saved plan, save another one, or clear it. A scenario's delivery alternative stays private to the scenario until you apply it; saving a scenario is not the same as saving the shared delivery plan. Booked deliveries and existing orders keep their own dates.

Refusals you may read ​

A schedule must add up to the whole buy:

An intake schedule must add up to the whole buy, 10000 basis points, which is 100%. This one adds up to {total} ({percent}%). It has not been saved and has not been adjusted.

A month outside the window is refused with the months it does cover:

This commitment's window does not cover {months}, so no part of its buy can land there. The months it covers are {first} to {last}.

If the delivery calendar is not set, the save is refused with "Set a delivery calendar first." If the reviewed schedule changed while you worked, it says "The reviewed phasing or its history changed; nothing was saved."