Where is this account's order plan, and what is the one thing to do next?
What you see
A strip above the forecast shows the plan's stages in order. Each stage has a name, a state in words and an icon, and the next stage with something to do carries its button.
| Stage | What it reads |
|---|---|
| Engine proposal | Units the engine proposes across its doors. Drawn only where an engine proposal exists |
| Proposed calendar | Forecasts not yet sent to the buyer |
| With buyer | Waiting for the buyer, or the buyer's counter, logged as a revision |
| Agreed | Forecasts both sides have agreed |
| Projected | Units in draft orders |
| Confirmed | Units in confirmed orders |
States are Done, In progress, Waiting, Needs you, Not yet and Not read. The last means the order book could not be read. Projected and Confirmed read the account's order book once a forecast is agreed. They report what the book holds, not that this plan produced it.
The engine stage shows only when a run exists
The engine stage is the engine's netting of the product you have open: the page reads it for that product and the commitment. It shows how many units the engine's doors order and across how many doors. Where the engine holds no forecast for the product, the stage is left out, the strip has five stages starting at Proposed calendar, and one tag says No engine forecast for this product. With no product open there is no engine stage.
Per-door netting
With a netting, the buy review and the door allocation drawer list one row per door:
forecast, less stock, less in transit, plus cover, equals need
The columns are Door, Forecast, − Stock, − In transit, + Cover, = Need, Phases and Packs. Forecast is the engine's median over the weeks netted. Phases are the receipt dates on the account's agreed cadence, each with its order; units round up to whole packs. Where no cadence is agreed the order is one delivery and a tag says so. A Buyer column appears when stock figures were entered for the buy: the engine's quantity struck through beside the quantity those figures give, with the difference as a chip. Need is never below zero. A stock figure the door did not report carries a tag: Estimated for a door that does not report, Buyer figure for one entered for the buy. A door whose stock or cover is unknown shows Stock unknown or Needs stock and a cover target and has no need, rather than a need of zero.
Under the table, each thing the engine could not settle is one tag in words, such as Stock unknown, Order past its date or Choose a pack; several of one kind share one tag with a count. The netting only reads; it saves nothing and creates no order.
Buyer proposal
When the buyer sends a copy of the forecast back, the Buyer proposal chip appears with the number of cells changed. The drawer lists each changed cell by store, variant and week: the shared figure struck, the proposed figure beside it, the difference as a chip, the buyer's reason and who gave it. The buyer's note and the totals sit above the list. Accept makes the proposal the shared forecast with your approval on it. Decline keeps the shared forecast and returns the copy to the buyer; a reason is required and the buyer sees it. A seat that may not approve reads the proposal and cannot answer it.
What to do
- Read the strip left to right; the button on it is the next act.
- With no forecast, press the button that starts one from the engine.
- Press Send to buyer for an unsent forecast, or Review the counter when the buyer countered. It opens the Buyer proposal drawer, which is also reached from the Buyer proposal chip beside the product's filters.
- Press Mark as agreed, then Set up the buy, then the button that opens the account's orders.
A button shows only if your seat may do the act.
When it is empty or failed
With no forecast and no engine proposal, the strip says no forecast exists for this commitment yet and offers the button that starts one. A seat that may not start one is told a planner does.